how to set up CC Calendar to see conflicting scheduling...

Support, Questions and Suggestions for the FM7 Version of CC Calendar.
Posts: 1
Joined: Tue Nov 30, 2004 2:24 pm
PostPosted: Tue Nov 30, 2004 2:41 pm
Hi Experts:

I am new to Filemaker and CC Calender.

I did manager to make my own project scheduling database based on CC Calender 7 and FM 7. So, under the day of choice, I can set up appointments/projects which include the time span, client, personnel, and equipment.

However, I have no idea how to set up the following:
When you enter a new project/appointment which requires Bob as a camerman, you will see an alert that tells you that he is already booked for another project which overlaps partially with the one you are setting up.

Please help if you have some suggestion. If you know how, please let me know how if you don't mind.

Thank you very much.

Erica
SeedCode Staff
SeedCode Staff
Posts: 2764
Joined: Thu Nov 20, 2003 11:01 am
PostPosted: Thu Dec 02, 2004 5:02 am
Hi. Glad to hear you're making such headway with the calendar! Doing conflicts is pretty straight forward and I've put together some instructions here:

http://www.seedcode.com/support/viewtopic.php?t=368

Let us know how it works for you!

Best,

John
John Sindelar
SeedCode

Return to CC Calendar (FM7/8)

Who is online

Users browsing this forum: No registered users and 2 guests

cron
(855) SEEDCODE
[email protected]
Follow us: