Bug Fix: Go to "Fancy" Week

Support for our integrated Contact Manager, Calendar, and Project Tracker.
SeedCode Staff
SeedCode Staff
Posts: 2764
Joined: Thu Nov 20, 2003 11:01 am
PostPosted: Sat Oct 28, 2006 9:57 am
We found an issue in the "fancy" week view in SeedCode Calendar versions 3.13 and prior where in some cases you can arrive at the wrong week when using the "Go to date..." routine.

To fix this in your copy, edit the script "Go to Selected Week" and change the calc in the first IF statement to this:

Code: Select all
PatternCount ( Get ( LayoutTableName ) ; "Sched" ) =0
and
CalendarMonth::CalDate1_k_Calc <= CalendarScheduling::CalFliterDateGlob
and
CalendarMonth::CalDate7_k_Calc  >=  CalendarScheduling::CalFliterDateGlob


That's it!
John Sindelar
SeedCode

Return to SeedCode Calendar

Who is online

Users browsing this forum: Google [Bot] and 2 guests

cron
(855) SEEDCODE
[email protected]
Follow us: